City of Glendale Audit Committee:
We are pleased to present our internal audit report on Departmental Coordination of the Capital Improvement
Plan (CIP) process as required by the City of Glendale’s (the City) FY25 Audit Plan. The internal audit objective was
to assess how multiple departments interact on projects to determine the level of coordination and cooperation,
identify reasons for delays, fixes, and communication or payment issues, and evaluate whether the City’s CIP
budget is appropriately aligned with current needs and financial capacity.
We have reviewed the results of our work with City management and appreciate the courtesy that was extended
to us by its staff.
Sincerely,
Jack Reagan
Managing Director
UHY Advisors Mid-Atlantic, Inc.
uhy-us.com
City of Glendale
Departmental Coordination Internal Audit
September 11, 2025
City of Glendale – Departmental Coordination
3
Table of Contents
Executive Summary ....................................................................................................................................... 5
Scope of Work ........................................................................................................................................... 5
Audit Results ............................................................................................................................................. 5
A. Governance and Communication ................................................................................................ 5
B. Procurement ................................................................................................................................ 5
C. Project Management ................................................................................................................... 5
D. Systems ........................................................................................................................................ 6
Recommendations .................................................................................................................................... 6
A. Governance and Communication Recommendations ................................................................. 6
B. Procurement Recommendations ................................................................................................. 7
C. Project Management Recommendations .................................................................................... 7
D. System Recommendations .......................................................................................................... 8
Audit Report ................................................................................................................................................ 10
Background ............................................................................................................................................. 10
Methodology ........................................................................................................................................... 10
Scope of Work ......................................................................................................................................... 10
Audit Results & Observations ................................................................................................................. 11
Governance and Miscommunication .................................................................................................. 11
Procurement ....................................................................................................................................... 12
Procurement Duration .................................................................................................................... 12
Procurement Method ..................................................................................................................... 12
Vendor Selection & Monitoring ...................................................................................................... 13
Project Management .......................................................................................................................... 13
Project Charter ................................................................................................................................ 13
Project Finance ................................................................................................................................ 14
Project Closeout .............................................................................................................................. 14
Key Performance Indicators (KPIs) .................................................................................................. 15
Systems ............................................................................................................................................... 16
City of Glendale – Departmental Coordination
4
Appendix A – City Staff Interviewed ........................................................................................................... 17
Appendix B – Engineering Management Responses ................................................................................... 18
City of Glendale – Departmental Coordination
5
Executive Summary
As part of the City of Glendale’s (the City) FY25 Audit Plan, we conducted a performance audit to assess
how various City departments interacted on Capital Improvement Plan (CIP) projects. The objective of
the audit was to assess the collaboration and coordination among multiple departments on these
projects, identify factors contributing to delays, necessary fixes, and issues related to communication or
payments, and evaluate whether the City’s CIP budget is appropriately aligned with current needs and
financial capacity.
The Engineering Department is responsible for executing the City’s CIP and ensuring the effective
management of major City projects throughout their lifecycle. Engineering collaborates with partner
departments across the City to ensure the successful delivery of completed CIP projects.
Scope of Work
The scope of work included CIP projects that involved Engineering, Water Services, Parks & Recreation,
Field Operations, Transportation, and Budget & Finance. The audit excluded departments that were not
involved in inter-departmental coordination with Engineering for CIP projects. Interviews were
conducted with management to gain an overview of the CIP process, understand stakeholder
departments' roles, and the staff's responsibilities. Walkthroughs were performed to identify
operational, compliance, and financial risks and internal controls, opportunities for improvement, and
root causes of inefficiencies. The periods reviewed for operational testing of controls ranged from fiscal
year 2024 to fiscal year 2025.
Audit Results
Overall, we identified opportunities for departmental coordination improvement across four key areas.
A. Governance and Communication
While Engineering developed the PM Lite Manual (the Manual) in response to prior audit findings, it
does not include some critical components, such as guidance on financial reporting. Additionally,
due to partner department staff turnover, the Manual has not been effectively communicated across
some departments or updated since its release.
B. Procurement
The overall CIP procurement function presents several challenges to project delivery, including
procurement durations, contract negotiation delays, absent vendor selection procedures, and
informal vendor performance monitoring. These weaknesses collectively increase the risk of project
inefficiencies, noncompliance with best practices, and reduced trust among departments and
stakeholders.
C. Project Management
While the Engineering Department has formalized its project management practices for CIP projects,
critical gaps affect project oversight, execution, and accountability. Specifically, project charters are
not utilized as an active functional tool that would be expected in project management to guide
City of Glendale – Departmental Coordination
6
execution; project budgets lack proper planning; financial reporting lacks transparency; project
closeout processes are inconsistently followed; and key performance indicators are neither
reasonably defined nor tracked.
These deficiencies collectively increase the risk of project delays, budget overruns, ineffective
resource use, missed warranty opportunities, project carryover, and reduced interdepartmental
coordination. Without addressing these weaknesses, the City’s ability to deliver CIP projects
efficiently, transparently, and within scope remains at risk.
We also found significant underutilization of allocated CIP funds. For fiscal years 2021 – 2025, the
City’s total CIP budget was $1,820,635,140. Engineering was responsible for delivering 60% of this
budget, totaling $1,085,638,265. Engineering was able to deliver about 50% of that budget, spending
$546,243,151. For projects managed outside of Engineering’s purview, the budget accounted for
40% of the total CIP, or $734,996,875, but only about 28% was expended ($202,592,642).
D. Systems
The Engineering Department currently relies on SmartSheet as its project management software and
data platform; however, the system falls short of meeting the complex demands of managing the
City’s CIP projects effectively. The software lacks critical features such as a comprehensive project
dashboard view for real-time tracking, a centralized warranty repository, system integration, file
backup, and advanced reporting capabilities. Without these features, Engineering faces significant
challenges in maintaining project visibility and generating actionable insights, highlighting the need
for a more powerful and integrated project management solution.
Recommendations
By implementing the recommendations below, the Engineering Department can reduce the risk of
project inefficiencies and enhance its ability to deliver CIP projects transparently, on time, and within
budget.
A. Governance and Communication Recommendations
The following are practical steps recommended to address the observations surrounding governance and
communication:
• Engineering should update the PM Lite Manual to include:
o A financial reporting component that outlines expectations for project-level financial monitoring,
including budget-to-actual tracking, carryover analysis, and documentation of budget
modifications.
o More clearly define partner departments' roles, responsibilities, and decision-making authority
throughout a CIP project. This should include input from partner departments on what needs to
occur during planning, execution, and closeout stages to ensure accountability and
collaboration.
• To ensure alignment across departments, Engineering should continue to execute its plan to
distribute the Manual to all partner departments and relevant stakeholders as soon as possible.
City of Glendale – Departmental Coordination
7
o It should also proceed with its Lunch and Learns to encourage dialogue with partner department
management regarding the Manual, ensuring a consistent understanding of its content and
expectations.
o After training has been completed, each partner department and stakeholder should formally
acknowledge, using a statement form, their understanding of the Manual’s expectations and
commitment to abide by the guidelines agreed upon.
• Engineering needs to implement an annual review process to ensure that policies and procedures,
such as the Manual, are current and reflect updates to operations and local and state regulations.
B. Procurement Recommendations
Below are actionable recommendations that should be taken to address procurement observations:
Procurement Duration – Establish a comprehensive procurement timeline tracking process that captures
the full duration of the procurement lifecycle, from project charter initiation through City Council
contract approval. This data will then be used to monitor performance against benchmarks, identify
delays, and improve project scheduling and resource planning.
Procurement Method – Enforce the use of a formal procurement plan for each CIP project to capture the
selected procurement method, rationale for its selection, key procurement milestones, responsible
parties, target timeframes, and anticipated risks or roadblocks.
Vendor Selection & Monitoring
• Establish formal, standardized criteria and procedures for vendor selection in the Manual to ensure
fairness, transparency, and alignment with City procurement policies. This should include guidance
on qualifications, evaluation criteria, scoring methods, and documentation requirements.
• Develop and adopt procedures for systematic vendor performance evaluations, including regular
assessments tied to contract milestones and completion. Require documentation of performance
issues, resolutions, and feedback from all departments involved. Engineering and partner
departments should have clearly defined roles in managing vendor performance, addressing
disputes or concerns, and following escalation protocols.
C. Project Management Recommendations
Outlined below are recommended actions to effectively address the project management observations:
Project Charters
• Revise the project charter framework to include comprehensive project management elements, such
as those listed below. This will ensure the charter serves as a living document that actively guides
project execution rather than just a procedural checkbox.
o Clearly defined scope and final outcome goals for each project
o Defined communication protocols and escalation paths
o Clearly identified departmental representatives and their contact information
o Detailed roles and responsibilities for all departments involved and key stakeholders
City of Glendale – Departmental Coordination
8
o Project timelines with milestones and critical path analysis
o Documented next steps and decision points for follow-up
Project Finance
• Government Finance Officers Association (GFOA) guidance states that CIP budgets should align with
project readiness and execution capacity. Partner departments should develop realistic financial
projections for year-over-year CIP projects that consider funding sources, operational capabilities,
carryovers, and data analytics to avoid overextending resources and ensure realistic spending and
delivery timelines.
o Once drafted, partner departments should work with Engineering to validate the reasonableness
of the proposed budget for each CIP project to ensure it reflects actual conditions and shared
priorities.
• To improve financial reporting transparency and consistency, engineering and partner departments
should implement a standardized financial reporting process for individual CIP projects that includes
budget-to-actual comparisons, forecast updates, and explanations for exceeding budget and
excessive carryover. Reports should be updated monthly and distributed to relevant stakeholders.
Project Closeout
• Enforce the project closeout procedures outlined in the Manual, including financial reconciliation,
completion letters, warranty tracking, and other pertinent documentation of completed work.
• Update the Manual to require closeout meetings for all CIP projects to discuss and document lessons
learned, successes, and areas for improvement. Representatives from Engineering, partner
departments, and key stakeholders should be included.
Key Performance Indicators
• Develop and adopt a set of shared and standardized KPIs to measure project performance. The KPIs
should be specific, measurable, achievable, relevant, and time bound. KPI examples include the
percent of projects with scope creep, measurement of creep itself, percent of projects delivered in
the CIP year it was programmed for, scope cost vs. final cost, schedule adherence, cost variance,
resource utilization, and contractor performance.
o Assign responsibility to the Budget & CIP Administrator or Principal Engineer for collecting and
reporting on KPIs and incorporating these metrics into regular management reviews to support
continuous improvement and decision-making amongst departments.
• Provide targeted project management training for Engineering and partner department project
managers on best practices in project planning, proper use of project charters, financial reporting,
and closeout. This will improve the coordination, accountability, and oversight of CIP projects
between Engineering and partner departments.
D. System Recommendations
The City should consider investing in an enhanced project management platform to support the CIP with
real-time updates, provide comprehensive dashboards and financial tracking, document control, and
City of Glendale – Departmental Coordination
9
multi-user collaboration features. Strengthening the CIP project management system will improve
transparency, accountability, and cross-departmental coordination throughout the project lifecycle.
• Engineering should collaborate with Finance, IT, and partner departments to research and identify a
suitable project management system, including both the RSOQ development process and evaluation
phase.
• In addition to the PM Lite Manual and project management training mentioned above, partner
departments and project stakeholders should also receive user training for the selected system.
City of Glendale – Departmental Coordination
10
Audit Report
Background
As part of the City’s Independent Internal Audit Program (IIAP) FY25 Audit Plan, UHY conducted a
performance audit of the departmental coordination within the Capital Improvement Plan process. The
Engineering Department is responsible for overseeing the City’s Capital Improvement Plan (CIP) by
guiding major construction projects from inception to completion. Engineering actively collaborates with
partner departments across the City to ensure projects are completed.
As part of the FY2022 Audit Plan, Moss Adams LLP conducted an audit to evaluate the City ’s CIP. The
objective was to assess the City’s capital planning, budgeting, forecasting, project identification, and
programming practices for adherence to best practices, ability to meet the City’s needs and strategic
goals, and efficiency and effectiveness.
The objective of UHY’s performance audit was to assess the level of collaboration and coordination
among departments involved in projects with Engineering. This included focusing on existing workflows
to identify factors contributing to delays, necessary improvements, and issues related to communication
and payments. Additionally, City management expressed concern about the “rightsizing” of the City ’s
CIP, and as a result, we also evaluated the City ’s CIP budget to actual amounts spent.
Methodology
We conducted our internal audit procedures by the Institute of Internal Auditors’ (IIA) Global Internal
Audit Standards (“Red Book”) and generally accepted government auditing standards (GAGAS),
commonly referred to as the “Yellow Book.” Those standards require that we plan and perform the audit
to obtain sufficient and appropriate evidence to provide a reasonable basis for our audit results and
conclusions. We believe that the evidence obtained provides reasonable assurance of our audit results
and conclusions based on the audit objective.
We conducted our internal audit procedures through the lens of the comprehensive Committee of
Sponsoring Organizations of the Treadway Commission (COSO) framework, its five components, and 17
internal control principles. The COSO framework also divides internal control objectives into three
categories: operations, reporting, and compliance. The COSO framework provides an applied risk
management approach to internal controls and aims to help organizations reduce fraud.
Scope of Work
The scope of work included CIP projects that involved Engineering, Water Services, Parks & Recreation,
Field Operations, Transportation, and Budget & Finance. The audit excluded departments that were not
involved in inter-departmental coordination with Engineering for CIP projects. Interviews were
conducted with management to gain an overview of the CIP process, understand stakeholder
departments' roles, and the staff's responsibilities. Walkthroughs were performed to identify
operational, compliance, and financial risks and internal controls, opportunities for improvement, and
City of Glendale – Departmental Coordination
11
root causes of inefficiencies. The time periods reviewed for operational testing of controls ranged from
January 2024 to December 2024. We reviewed an assortment of documentation, including but not
limited to:
• FY 24 and FY25 CIP
• FY 24 and FY25 Budget Book
• PM Lite Manual
• Project Charters
• SmartSheet Tracker
Audit Results & Observations
Through interviews with Engineering and partnering departments and review of documentation, we
observed that some components of the City ’s CIP process and departmental collaboration need
additional improvement.
Governance and Miscommunication
The FY22 CIP audit identified that the City lacked formal policies and procedures to guide key aspects of
the CIP. As a result, Engineering developed the Project Manager's Manual for the Procurement, Study,
Design, and Construction of Capital Improvement Plan Projects, which the department refers to as the
PM Lite Manual (the Manual). Our review found that the Manual contains key components such as
project initiation, scheduling, progress communication, closure, and Engineering’s role and
responsibilities. The expected responsibilities for partner departments are also embedded within the
Manual. However, it does not include a financial reporting component that outlines what financial
monitoring is essential for individual CIP project transparency and successful completion within budget.
Additionally, some partner departments expressed that Engineering has not effectively communicated or
distributed the Manual to better understand and collaborate on their expected roles and responsibilities
in joint CIP projects. Engineering has held internal training sessions with some partner departments,
which were accomplished through a “Lunch & Learn” initiative. Lastly, there is no evidence that the
Manual has been reviewed or updated since it was published in November 2023.
The Government Finance Officers Association's best practices recommend that governments establish
and maintain formal policies and procedures for capital planning, which include financial oversight, role
clarity, interdepartmental collaboration, and regular updates to policies and manuals to reflect current
practices and risks. The Project Management Institute (PMI) standards also outline that project
management frameworks should include defined roles and responsibilities of all stakeholders.
The lack of financial reporting guidance for individual CIP projects may contribute to the budget overruns
and carryovers experienced in the City’s overall CIP. If partner departments are not consulted on their
expected roles and responsibilities when involved in a CIP project managed by Engineering, it will
continue to lead to coordination gaps, accountability issues, and duplicative efforts.
City of Glendale – Departmental Coordination
12
Procurement
Procurement Duration
Engineering’s Budget & CIP Administrator has been granted delegated authority by Finance for Title 34
procurement, which consists of public buildings and improvements per the Arizona Legislature. The
Administrator utilizes an Excel spreadsheet to track the Request For Quotation (RFQ) procurement
duration only from the date of vendor (Contractor) selection to the contract approval date by the City
Council. For a sample of 5 projects, we compared the project charter start date to dates on Engineering’s
RFQ spreadsheet and found that 3 of 5 projects had a procurement lead time that exceeded 60 days.
The City's full RFQ process typically consists of sending notice to the City clerk, running an ad, running a
second ad, pre-submittal, time to score, selecting a vendor, negotiating with the selected vendor, and
contract approval by the City Council.
Engineering considers the procurement process completed once a vendor is selected, which should
typically take about 49 days. However, when considering all the procurement steps up to contract
approval, the total procurement time can be up to 8 months.
Procurement lead times and contract negotiation delays present challenges to timely project delivery.
Without fully accounting for the complete procurement timeline from project charter initiation through
City Council contract approval, the City may underestimate project schedules, misalign resources, and
contribute to project delays, increased costs, and diminished coordination between partner
departments.
Procurement Method
The Manual contains details of the pros and cons of each procurement method and includes a list of 20
criteria that should be considered when selecting the procurement method for specific projects. Using
this information, we attempted to validate that the procurement method selected and documented in
the project charter aligned with procurement policy guidelines. However, since the delivery methods
used vary from project to project, we were unable to validate the procurement decision-making efforts
for the projects sampled. A project procurement plan is also not currently documented as part of the
project charters.
The Manual’s Pre-Selection Activities section references a project procurement plan to be established as
part of the Partner/Engineering project charter. Project teams also rely on informal judgment and
experience without standardized guidance or documented justification for the chosen procurement
approach.
If a formal project procurement plan is not documented, the City risks inconsistent and potentially
inappropriate procurement decisions. This lack of documentation reduces transparency and may lead to
delays, inefficiencies, or noncompliance with City procurement expectations, ultimately impacting the
timely and cost-effective delivery of capital projects.
City of Glendale – Departmental Coordination
13
Vendor Selection & Monitoring
Our review found that the Manual does not include guidance for vendor selection to ensure fairness and
transparency. Additionally, formal vendor performance monitoring procedures to ensure contract
compliance are absent. As a result, we could not validate that vendor selection and monitoring are done
in compliance with the Manual or best practices.
Engineering and partner departments should utilize a vendor management tool that tracks contract
terms, end dates, and performance. Vendor and contract management best practices emphasize the
need for systematic and documented performance evaluations to ensure quality, managed risk, and
support informed procurement decisions.
Vendor performance feedback is handled informally and only when significant issues arise, often through
dialogue between Engineering and the partner department(s), potentially leading to disagreement. It is
also unclear whether Procurement, which oversees Vendor Self-Service, maintains vendor performance
tracking.
The absence of explicit vendor selection guidelines creates a misalignment between Engineering and
partner departments regarding acceptable practices for vendor selection. It also creates a risk for
potential vendor favoritism, kickbacks, and vendor overload. Without systematic vendor monitoring and
contract oversight, the City is at greater risk of awarding contracts to underperforming vendors,
overlooking compliance issues, making uninformed future procurement decisions, and experiencing
strained interdepartmental coordination.
Project Management
Effective project management is critical to the successful delivery of the City ’s CIP within budget and on
time. Our review found gaps in key project areas such as project charters, financial reporting, and project
closeout that can affect the execution and oversight of Engineering’s project management.
Project Charter
Engineering has implemented the use of project charters to kick off its responsibility of project
management over a CIP project and to serve as a shared agreement among stakeholders. A project
charter is completed as a procedural step in Engineering’s project management rather than used as a
functional tool that guides project execution. As a result, we found that a sample of project charters did
not include common project management elements such as defined communication protocols, clearly
identified departmental representatives, roles and responsibilities for each department involved in the
project, milestones, and documentation of next steps.
Engineering defines a project charter as an interdepartmental agreement on project parameters such as
scope, schedule, and budget. The use of project charters is a result of those parameters not being clearly
communicated and agreed upon previously between Engineering and partner departments. Engineering
did not intend for a project charter to serve as a robust and active project management tool.
Failing to utilize a project charter as a dynamic tool incorporating essential project management
elements increases risks that may impede project success and lead to inefficient resource use. Without
City of Glendale – Departmental Coordination
14
clear roles, responsibilities, and communication channels, project stakeholders across departments
struggle to work together effectively, impacting project productivity and morale.
Project Finance
There is a gap for financial transparency in CIP projects that limits the ability of Engineering to monitor
and communicate financial performance with partner departments effectively. We reviewed 75 CIP
projects involving Engineering and found that 11 (15%) were over budget before requesting additional
funding approval. We also found that $166,002,131 was carried over from FY24 into FY25 for 14 project
types. The five projects with the highest carryover totaled $34,240,057. Per Engineering’s tracking, four
of the five projects had carryover exceeding 80% of their budget amounts. SmartSheet also did not
include comprehensive financial updates, such as a budget-to-actual analysis; only high-level notes of
payment applications were included.
A standard process for monitoring and disclosing financial information by Engineering to project
stakeholders throughout the project lifecycle is essential to ensure transparency, enable informed
decision-making, and support proactive financial management. The audit team was unable to obtain
documentation for budget modifications to fully assess the validity, accuracy, and process of budget
modifications incorporated into the CIP.
Engineering indicated that amounts documented on project charters are only an initial estimate of a
project, and the City ultimately identifies funding that can be used to complete projects that exceed its
budget. Rather, budget transfers are performed by partner departments so that actual expenditures do
not exceed the original budgets approved by the City Council.
Additionally, upon inquiry into the root causes of carryover amounts, Engineering and partner
departments communicated that carryover amounts can be caused by various reasons, including
misalignment between project timelines and funding cycles, budget overestimates leading to funds
being unused in a fiscal year, inefficiencies in project execution, procurement bottlenecks, project scope
changes, staff shortages, contractor availability, and funding constraints.
The absence of a standardized financial disclosure process limits Engineering’s ability to consistently
track budget changes, understand the underlying causes of carryover amounts, and communicate
effectively with partner departments. As a result, project stakeholders may not have access to complete
or timely financial information needed to support informed decision-making and ensure effective
oversight of project budgets. This lack of financial visibility also results in budget inefficiencies,
undetected inconsistencies, misaligned resource allocation, errors within final reporting, and diminished
oversight of CIP project execution.
Project Closeout
Engineering’s project closeout process is either absent or inconsistently applied, as completion letters
are not always obtained in a timely manner, and warranty information is not retained or shared with
partner departments.
City of Glendale – Departmental Coordination
15
The Manual indicates that the Engineering PM, consultant, and contractor should sign off on a final
completion letter. A copy of the letter is to be placed in the project file, and the warranty will begin on
the date indicated on the letter.
The Manual also outlines project closeout: “After the project is accepted and the Consultant and
Contractor have been paid, the PM may entertain a project closeout meeting with the Engineering and
Partner Department representatives at the Engineering Department Director ’s direction. The purpose of
this meeting will be to discuss the overall outcome of the project (issues, successes, and lessons applied
to future projects). This meeting’s intent is to serve as an avenue for possible process improvements as
well as a discussion of areas of success or areas of improvement that might be necessary, NOT to finger-
point, etc.”
Our review found that post-project collaboration is limited, as closeout meetings are optional rather than
mandatory. Furthermore, the current process for managing warranties relies on Microsoft Outlook
reminders to schedule inspections two years after project completion. The Outlook calendar invite
includes a trigger and invites relevant City staff, consultants, and contractors. Multiple representatives
from each stakeholder group are included to account for turnover, such as promotions, retirements, or
resignations. While this approach ensures some continuity, no formal or centralized system is in place to
verify warranty documentation or track maintenance logs to ensure timely warranty claims.
Although Engineering has taken steps to improve the project closeout process, it remains inconsistent,
which limits the ability of project stakeholders to capture and apply lessons learned to future projects.
Without a formal project management software system, Engineering will continue to rely on Outlook
and SmartSheet, which lack the functionality to serve as a centralized repository for warranty
information. There is a risk that warranty claims may be missed or delayed, resulting in avoidable repair
costs to the City.
Key Performance Indicators (KPIs)
The FY22 CIP audit found that the City had not developed a standardized annual CIP report to track
progress and performance. As a result, Engineering identified three key metrics in their PM Lite Manual
intended to demonstrate the department’s ability to deliver the CIP; however, the department does not
currently track or monitor these metrics. The three Engineering metrics include:
1. 95% of invoices are processed within the department within 7 days.
2. 100% of projects are completed on time.
3. 95% of warranty inspections do not result in rework.
Engineering does not have the appropriate tools to easily track, analyze, and report on department
metrics. The KPIs referenced in the 2023 PM Lite Manual may benefit from clearer definitions and more
attainable targets, as their current form may have led to a lack of motivation to track them.
Without proper and relevant KPIs, Finance, Engineering, and partner departments are limited in their
ability to objectively assess their performance in delivering CIP projects. Combined with the absence of
tracking established metrics, Engineering does not have sufficient and reliable data to identify areas for
improvement, demonstrate accountability, and ensure projects meet quality, timeliness, and financial
City of Glendale – Departmental Coordination
16
goals. Ultimately, these gaps may reduce stakeholder confidence in Engineering’s project management
effectiveness.
Systems
Engineering utilizes SmartSheet as its CIP project management software. We reviewed a sample of five
projects to determine whether they were included and tracked in SmartSheet and found no exceptions.
We found project progress to be documented at least monthly by Engineering, with editing restricted
solely to Engineering and read-only access for partner departments. We also found SmartSheet to be an
insufficient project management tool that limits detailed project timelines/milestones, comprehensive
financial reporting, two-way communication and note documentation, and data-driven decision-making.
Engineering should use a project management tool that better supports the City’s growing CIP and
allows for a dashboard view of project progress, a centralized warranty repository, version control, file
backup, integration with other systems, and advanced reporting capabilities.
Due to funding limitations, Engineering has been unable to procure and implement more robust project
management software that would allow for improved transparency, accountability, collaboration, and
effective communication channels. Without the appropriate tools, project stakeholders are unable to
readily assess project performance, identify areas for improvement, and strengthen real-time
collaboration and two-way communication.
City of Glendale – Departmental Coordination
17
Appendix A – City Staff Interviewed 1
Donald Bessler, Director, Engineering Department (now retired)
*Ron Serio, Director, Water Services Department
*John Kennedy, Director, Parks & Recreation Department
*Michelle Woytenko, Director, Field Operations Department
Levi Gibson, Director, Budget and Finance Department
*Purab Adabala, Director, Transportation Department
*John Murphey, Administrator Budget & CIP, Engineering Department
*Tom Kaczmarowski, Principal Engineer, Engineering Department
*John Henny, Deputy Director, Water Services Department
*Mark Roye, Deputy Director, Water Services Department
*Stephen Acquafredda, Principal Engineer, Water Services Department
*Jenny Doyle, Senior Civil Engineer, Water Services Department
*Heidi Barriga, Deputy Director, Parks & Recreation Department
*Michael Keane, Assistant Director, Parks & Recreation Department
*Daren Frank, Deputy Director, Field Operations Department
*Michael Carr, Deputy Director, Field Operations – Landfill
*Craig Croner, Deputy Director, Field Operations – Fleet
*Jonathan Hill, Budget Administrator, Budget and Finance Department
Vision CIG (Capital Improvement Glendale) Team Members not already listed
Jamsheed Mehta, Assistant City Manager, City Manager’s Office
Djordje Pavlovic, Director, Engineering
Gene Haranczak, CIP/Engineering Project Manager, Engineering
Jonathan Flatt, Admin-Civil Engineer, Engineering
Tangella Diaz, Admin-Real Estate, Engineering
Jenny Durda, Director, Organizational Performance
Jeff Bratcher, Organizational Performance Officer, Organizational Performance
Stephen Gushue, Business Intelligence & Analytics Officer, Organizational Performance
Fred Sanchez, CIP/Engineering Project Manager, Parks & Recreation
Julian Reyes, CIP/Engineering Project Manager, Parks & Recreation
Sam Chiovari, Superintendent, Parks & Recreation
Tony Abbo, Deputy Director, Transportation
Matt Smith, Airport Administrator, Transportation
Javier Gurrola, Principal Engineer, Transportation
Erin Steffa, Financial Analyst, Transportation
1 Staff with * next to their names are part of the Vision CIG Team
City of Glendale – Departmental Coordination
18
Appendix B – Engineering Management Responses
RE: Management’s Corrective Action Plan Departmental Coordination Internal Audit
Recommendation(s)
# Description Audit
Report
Page
Accept/
Decline
Responsible
Person’s
Name/Title
Completion
Date
A Governance and Communication
• Engineering should update the PM
Lite Manual to include:
o A financial reporting component
that outlines expectations for
project-level financial
monitoring, including budget-to-
actual tracking, carryover
analysis, and documentation of
budget modifications.
o More clearly define partner
departments' roles,
responsibilities, and decision-
making authority throughout a
CIP project. This should include
input from partner departments
on what needs to occur during
planning, execution, and
closeout stages to ensure
accountability and collaboration.
• To ensure alignment across
departments, Engineering should
execute its plan to distribute the
Manual to all partner departments
and relevant stakeholders as soon as
possible.
o It should also proceed with its
Lunch and Learns to begin a
dialogue with partner
department management
regarding the Manual, ensuring
a consistent understanding of its
content and expectations.
o After training has been
completed, each partner
department and stakeholder
should formally acknowledge,
using a statement form, their
understanding of the Manual’s
10
A1.1 - accept
A1.2 - accept
A2.1 - accept
A2.1.1 –
accept with
modifications
A2.1.2 –
decline
Vision CIG
Team
7/31/2026
City of Glendale – Departmental Coordination
19
expectations and commitment
to abide by the guidelines
agreed upon.
• Engineering needs to implement an
annual review process to ensure that
policies and procedures, such as the
Manual, are current and reflect
updates to operations and local and
state regulations.
A2.1.3 –
accept with
modifications
Action Plan:
A1.1-2. A Lean Project to improve coordination, communication, and partnership between all
departments who participate in the CIP has been initiated. One of the tasks of this Lean Project team,
now called Vision CIG (Capital Improvements for Glendale), is to respond to the audit findings and
subsequently have the Engineering Department update the manual. The team has agreed that
financial reporting standards should be included in each project charter and will be added to the PM
Lite Manual at a high level. The team also identified a gap in communication standards and details
about project execution. A major focus of the Vision CIG Team is to clearly define all department
responsibilities and decision-making authority.
A2.1. This recommendation has been implemented. All departments have been provided a copy of the
PM Lite Manual for their review. Additionally, the Vision CIG team will conduct a thorough review,
make updates, and distribute future revisions as needed.
A2.1.1 – 3. The Vision CIG Team has determined that two annual workshops will be held, one a past
year review and at least one training. The annual review will be held in late summer to review the
past year and determine how collaboration can be improved. The team will document lessons
learned, coordinate CIP Lite Manual updates, and determine what CIP-related training(s) need to
occur in the coming year. Training sessions will be hosted by Engineering and partner departments
may assist in trainer or presenter roles. The “Lunch and Learn” format will continue as the primary
method of training delivery.
A2.1.2. Given the decision to add an annual workshop that includes a manual review process, the
Vision CIG Team does not feel that an acknowledgement form is necessary or value-added. However, a
sign in sheet may be utilized during the workshops and training sessions to ensure follow-up
information is provided to key stakeholders as necessary.
City of Glendale – Departmental Coordination
20
B Procurement
• Establish a comprehensive
procurement timeline tracking
process that captures the full
duration of the procurement
lifecycle, from project charter
initiation through City Council
contract approval. This data will then
be used to monitor performance
against benchmarks, identify delays,
and improve project scheduling and
resource planning.
• Enforce the use of a formal
procurement plan for each CIP
project to capture the selected
procurement method, rationale for
its selection, key procurement
milestones, responsible parties,
target timeframes, and anticipated
risks or roadblocks.
• Establish formal, standardized
criteria and procedures for vendor
selection in the Manual to ensure
fairness, transparency, and
alignment with City procurement
policies. This should include
guidance on qualifications,
evaluation criteria, scoring methods,
and documentation requirements.
• Develop and adopt procedures for
systematic vendor performance
evaluations, including regular
assessments tied to contract
milestones and completion. Require
documentation of performance
issues, resolutions, and feedback
from all involved departments.
Engineering and partner
departments should have clearly
defined roles in managing vendor
performance, addressing disputes or
concerns, and following escalation
protocols.
11 –
12
B1 - Accept
B2 - Accept
B3 - Accept
B4 - Accept
Vision CIG
Team
07/31/2026
B1. The Vision CIG Team will work with Engineering to further define the existing CIP procurement
timeline, negotiations, including clearly identified milestones and accountability, for inclusion in the
project charter. These standards and procedures will also be updated within the PM Lite Manual.
Finally, the Vision CIG Team will evaluate automated dashboard options to provide project team
City of Glendale – Departmental Coordination
21
members with real-time visibility into project timelines, critical paths, current status, and potential
delays.
B2. A formal procurement plan will be established by the project team as part of the project charter
process with partner departments. The Engineering department will ensure compliance with
applicable procurement rules, standards, and Arizona statutes.
B3. Within the PM Lite Manual, the Vision CIG Team will define formal, standardized criteria and
procedures for vendor selections in compliance with city procurement rules and standards. Focus
areas include: the balance of staff on vendor selection committees, vendor selection criteria, JOC
contractor selection, and the equitable spread of spend-to-date work amongst contracted firms, as
appropriate or justified.
B4. The Vision CIG Team will review current vendor selection and evaluation methodologies within
Engineering and partner departments to establish a standardized approach that can be adjusted as
needed based on specific project needs. The team will evaluate best practices, such as Results Driven
Contracting, to improve contractor performance.
C Project Management
• Revise the project charter
framework to include
comprehensive project management
elements, such as those listed below.
This will ensure the charter serves as
a living document that actively
guides project execution rather than
just a procedural checkbox.
o Clearly defined scope and final
outcome goals for each project
o Defined communication
protocols and escalation paths
o Clearly identified departmental
representatives and their
contact information
o Detailed roles and
responsibilities for all involved
departments and key
stakeholders
o Project timelines with
milestones and critical path
analysis
o Documented next steps and
decision points for follow-up
• Government Finance Officers
Association (GFOA) guidance states
that CIP budgets should align with
project readiness and execution
capacity. Partner departments
12 –
14
C1 – Accept
with
clarification
C2 Accept
Vision CIG
Team
Vision CIG
Team
7/31/2026
City of Glendale – Departmental Coordination
22
should develop realistic financial
projections for year-over-year CIP
projects that consider funding
sources, operational capabilities,
carryovers, and data analytics to
avoid overextending resources and
ensure realistic spending and
delivery timelines. Once drafted,
partner departments should work
with Engineering to validate the
reasonableness of the proposed
budget for each CIP project to
ensure it reflects actual conditions
and shared priorities.
• To improve financial reporting
transparency and consistency,
Engineering and partner
departments should implement a
standardized financial reporting
process for individual CIP projects
that includes budget-to-actual
comparisons, forecast updates, and
explanations for exceeding budget
and excessive carryover. Reports
should be updated monthly and
distributed to relevant stakeholders.
• Enforce the project closeout
procedures outlined in the Manual,
including financial reconciliation,
completion letters, warranty
tracking, and other pertinent
documentation of completed work.
• Update the Manual to require
closeout meetings for all CIP projects
to discuss and document lessons
learned, successes, and areas for
improvement. Representatives from
Engineering, partner departments,
and key stakeholders should be
included.
• Develop and adopt a set of shared
and standardized KPIs to measure
project performance. The KPIs
should be specific, measurable,
achievable, relevant, and time
bound. KPI examples include the
percent of projects with scope creep,
measurement of creep itself, percent
C3 - Accept
C4 - Accept
C5 - Accept
C6 - Accept
Vision CIG
Team
Vision CIG
Team
Vision CIG
Team
Vision CIG
Team
City of Glendale – Departmental Coordination
23
of projects delivered in the CIP year
it was programmed for, scope cost
vs. final cost, schedule adherence,
cost variance, resource utilization,
and contractor performance.
o Assign responsibility to the
Budget & CIP Administrator or
Principal Engineer for collecting
and reporting on KPIs and
incorporating these metrics into
regular management reviews to
support continuous
improvement and decision-
making amongst departments.
• Provide targeted project
management training for
Engineering and partner department
project managers on best practices
in project planning, proper use of
project charters, financial reporting,
and closeout. This will improve the
coordination, accountability, and
oversight of CIP projects between
Engineering and partner
departments.
C7 - Accept
Engineering
Leadership
Action Plan:
C1.1. The Vision CIG Team agrees that revising project charter elements, such as the project scope,
would be beneficial. However, the team also recognizes that establishing a clear process for refining
the scope after initial research is more critical to a project’s overall success than attempting to fully
define the scope prior to initiating research or securing resources. The Vision CIG Team will evaluate
when and to what level of detail, scope refinement should occur.
C1.2. As part of the Lean Project, the Vision CIG Team will ensure that the project charter
communication plan is updated and includes a template with robust communication protocols and
escalation paths.
C1.3. As part of the Lean Project, the CIG Team will expand the charter’s Department Representatives
Section to ensure that all key stakeholders are included and provide more detail on roles and
responsibilities, referencing the PM Lite Manual where necessary. An “opt in or out” method for all
CIP Projects will be implemented, allowing each department to indicate whether they or a vendor
they work with, should collaborate on any particular project.
C1.4 The project timeline section will be enhanced, with an agreed upon methodology for revising the
timeline as the project moves forward.
C1.5 A standardized template will be included in the project charter to document routine next steps as
well as unique, project-specific requirements, with clearly assigned tasks and targeted completion
dates.
City of Glendale – Departmental Coordination
24
C2. The first phase of the Lean Project is focused on CIP project execution; upon completion, the
second phase of the project will follow and focus on improving CIP budgeting, planning, and financial
projections to improve efficiency and alignment with execution capacity.
C3. CIP financial reporting currently lacks consistency across departments; the Lean Project will
identify best practices and evaluate standardized, automated reporting and dashboard tools to
provide timely, consistent financial visibility for all departments.
C4. To ensure project closeout procedures are consistently followed, the team will review and
enhance current procedures, including financial reconciliation, completion letters, warranty tracking,
capital asset documentation, and a robust maintenance turnover process.
C5. As part of the Lean Project, the team will determine a standardized process for CIP project
closeout meetings, incorporating best practices for after-action reviews to document lessons learned,
successes, and areas for improvement, with participation from Engineering, partner departments, and
key stakeholders.
C6.1. The Vision CIG Team will develop and adopt a set of shared, standardized KPIs to measure CIP
project performance, including both overarching program and project-specific measures. The KPIs
shall account for differences between functional areas, balance project quality versus output, and
remain flexible to meet stakeholder needs.
C6.2. The Department of Engineering will serve as the primary custodian for the reporting of CIP Key
Performance Indicators (KPIs). Project Teams will collaborate on data collection, analysis, and
management reviews to support CIP continuous improvement.
C7. Engineering has already begun scheduling of professional development sessions for Engineering
Project Managers. Partner departments’ Project Managers will also complete project management
training.
D Systems
The City should consider investing in an
enhanced project management platform
to support the CIP with real-time
updates, provide comprehensive
dashboards and financial tracking,
document control, and multi-user
collaboration features. Strengthening the
CIP project management system will
improve transparency, accountability,
and cross-departmental coordination
throughout the project lifecycle.
•Engineering should collaborate with
Finance, IT, and partner departments
to research and identify a suitable
project management system,
including both the RSOQ
15 Accept Engineering,
Finance, IT
Directors
As part of
the FY 27
Budget
process
City of Glendale – Departmental Coordination
25
development process and evaluation
phase.
•In addition to the project
management training mentioned
above, partner departments and
project stakeholders should also
receive user training for the selected
system.
Action Plan:
D1.1 The Vision CIG Team will conduct a thorough needs assessment of the current project
management platform to validate system requirements to identify a software solution to best support
our processes. The software of choice should allow for efficient and timely input of information by
users, streamline cross-departmental coordination, and improve tracking of purchase order spending
throughout the project lifecycle to enhance transparency and accountability.
D1.2. If a new project management platform is deemed necessary, Engineering will serve as the lead
for the software procurement effort, collaborating with Finance, IT, and partner departments
throughout the requisition and evaluation phases to identify a viable project management system.
D1.3. Engineering, in coordination with Finance and IT, will ensure that all partner departments and
other key stakeholders that require system access receive the appropriate level of system training
during the integration phase. Engineering is already reviewing current access to see where additional
access is needed for partner departments.