City of Glendale
G Council Sustainability Committee
Minutes
May 15, 2012
10:30 a.m. to 11:30 a.m.
Conference Room B-2
Council Sustainability Committee Members:
Present were Vice Mayor/Chairperson Steve Frate (Sahuaro District),
Councilmember Yvonne Knaack (Barrel District)
City Staff Members:
Present were Marilyn Clark, Jon Froke, Ron Gouger, Craig Johnson, Stuart Kent,
Doug Kukino, Bob Manginell, Deborah Mazoyer, Greg Rodzenko, Erik Strunk, Brad
Tarrant, Pam Wertz, Michelle Woytenko
I. Approval of the Minutes of the January 17, 2012 Meeting
The minutes of the January 17, 2012 meeting were approved as written.
II. City Facility Enhancement Projects (EECBG Funded) Presentation
Stuart Kent, Executive Director, Public Works introduced Michelle Woytenko, Deputy
Director, Public Works who presented this agenda item.
In 2010, the City of Glendale received an Energy Efficiency and Conservation Block
Grant in the amount of $2.32 million. The condition of the grant requires the City to
use the funds in a cost-effective manner that creates jobs, reduces long-term energy
use, reduces greenhouse gas emissions, and saves energy over the life of the
project. Staff identified projects for the grant that emphasized savings in energy and
maintenance, and improved safety.
The distribution funds for this grant included $986,000 for Water Reclamation UV
improvements, $173,000 for the Energy Matters Public Education Program,
$107,000 Program Manager for EECBG Projects, $98,000 for Well 43 Variable
Frequency Drive, $86,000 for Traffic Signal LED Conversion, $35,000 for a Building
Safety Energy Program, and $840,000 for Facilities Lighting Retrofits, which is the
focus of this presentation.
Council Sustainability Committee
May 15, 2012
Page 2
City Annual Electricity Costs
Facilities Maintenance noticed an alarming trend that started in 2004-2005 where
the cost for electricity in city buildings had substantially increased. The kilowatt-hour
consumption was up, but not to the same volume as cost. From 2004 to 2008, the
actual cost per kilowatt-hour increased from $0.06 to $0.10. To help manage the
rising costs of electricity, Facilities Maintenance identified areas throughout the city
where lighting upgrades were needed the most. This upgrade project would consist
of replacing outdated and less energy efficient T-12 lamps with the more energy
efficient T-8 lamps.
Ninety-five percent of the energy that goes into a light is converted to heat, and five
percent is actually used for lighting. With the T-12 lamps, the amount of heat
emanating from these fixtures would be enough to cause an extra load to cool a
building, raising cost and energy usage, so replacing these fixtures was a smart
choice.
As manufacturers began phasing out production of the T-12 lamps, local utility
companies such as Arizona Public Service were offering incentives such as rebates
to help offset the cost of the upgrade.
Lighting Conversion
Facilities Maintenance took it a step further by converting fixtures from one lamp to
those with multiple lamps. Using multiple lamps not only enhances the quality of the
lighting output, but it reduces the number of maintenance trips, which saves time
and money.
Sport Courts
Facilities Maintenance looked at tennis, handball, and basketball courts with
representatives from the Parks & Recreation, Code Enforcement, and the Police
Department that had issues with either vandalism or graffiti. Eleven City parks,
O'Neil, Rose Lane, Bonsall North, Mary Silva, Sonorita, Clavelito, Glendale High,
Sands, Cholla, Acoma, and Chapparal received new lighting upgrades, representing
179 fixtures in all. This project has now been completed. The annual cost savings
for the City was $12,472 in energy savings with 133,540-kilowatt hours of energy
saved. The $16,050 Arizona Public Service Rebate that the City received will be
turned back into energy saving projects.
Main Library
The Main Library was a large project where the entire lighting system was
redesigned throughout the building. The savings on this project allowed for
additional energy enhancements to be made where exterior lighting was installed
and occupancy sensors were added inside the building. The $457,000 received for
this project represents about half the funding for all the lighting conversion projects
that were in the grant. Annual energy cost savings for this project was
approximately $18,690 with 169,970-kilowatt hours of energy saved.
Council Sustainability Committee
May 15, 2012
Page 3
Public Safety Court Complex and Parking Garage
The Public Safety Court Complex was initially planned to be just an interior project
replacing ballasts and lamps, converting from the old T-12 technology to the new T-8
technology. The City saved about $30,000 in actual savings on the interior portion
of the project with a rebate of approximately $22,080. Over 4500 bulbs in over 2000
fixtures were replaced for this project.
With the significant amount of cost saving involved with this project, Facilities
Maintenance submitted a request to the Department of Energy to add the parking
garage to this project. This enhancement would reduce electrical usage and provide
a safe, well-lit place to park. The energy savings on the parking garage portion of
the project was somewhere around $5,000 per year with an $11,400 rebate.
Equipment Management
The Sports Court, Main Library, and the Public Safety Court Complex/Parking
Garage represent what was initially proposed to complete the $840,000 grant. With
additional funds remaining in the grant, it was decided to add Equipment
Management to the list of projects.
Equipment Management is responsible for the repair and maintenance of the City's
vehicles. It provides fleet and equipment services out of a 70,000 square foot
facility. There are 99 fixtures across the tire shop, heavy duty, light duty, and make
ready areas. The facility was using a single bulb per fixture, and with the high
ceilings, it required a lift to replace the light bulbs. This type of bulb is subject to
early failure if the lights were continually turned on and off. As a result, the lights
needed to stay on 24 hours a day. If this did not occur, it would result in more
maintenance time. The facility is also evaporative cooled, so there was also a need
to reduce the amount of heat generated inside the building during the summer
months. The replacement of these fixtures reduces the amount of maintenance
trips, and improves productivity. The systems estimated annual cost savings for this
project was $12,152 with 180,252-kilowatt hours of energy saved. A rebate
application for$14,850 was submitted for this project.
Material Recovery Facility
The Material Recovery Facility located at the Glendale Municipal Landfill site was
another project added to the grant. The facility has 51 light fixtures. Issues with this
facility again, were the single bulb. The lighting over the sorting conveyors
presented several maintenance challenges, as the piles of incoming material had to
be moved in order to change the light bulbs. The estimated annual energy savings
for this project was $11,299 with 110,760-kilowatt hours of energy saved. There
was no rebate associated with this project.
Glendale Municipal Office Complex Parking Garage
Another addition to this grant was the parking garage at the Glendale Municipal
Office Complex. Since the replacement of 244 fixtures, the security issues have
Council Sustainability Committee
May 15, 2012
Page 4
gone away. This project yielded approximately $7,000 in annual cost savings along
with a rebate that was submitted for $16,500. This project was contracted out which
fit into nicely with the grant's goal of creating jobs in the community.
Downtown Parking Garage
The grant was also used to switch out 420 fixtures at the City's Downtown Parking
Garage. Even though this is a newer facility, the technology is changing rapidly.
The grant also helped to drive down the cost of materials. The annual cost savings
for this project was estimated to be around $7,460 with 114,416-kilowatt hours of
energy saved. The Arizona Public Service Rebate was submitted for $31,500.
Overview of Completed Projects -Costs and savings
Location Project Cost Annual Energy Savings Rebate
Sports Courts $ 64,910 $12,472 $16,050
Main Library $457,571 $18,690
Public Safety/Court Complex $ 60,650 $30,000 $33,480
Equipment Management $ 40,251 $12,152 $14,850
Material Recovery Facility $ 11,340 $11,299
GMOC - Parking Garage $ 57,571 $ 7,000 $16,500
Parking Garage - Downtown $ 65,708 $ 7,460 $31,500
Totals $758,001 $99,073 $112,380
Next Steps
Glendale recently received approval from the Department of Energy to replace some
of the lighting in City parks with solar lighting. The $99,073 in energy savings and
$112,000 received in rebates will be used for this project.
The initial proposal for this project included the four top parks, Sunset Ridge, Butler,
Sunnyside, and Sunset Palms. Parks were selected based on copper theft
concerns, maintenance requirements, cost to upgrade or replace, and vandalism.
The City recently advertised an Invitation for Bid for solar lighting fixtures in four of
the City's parks. The Initial bid was structured for four parks, but after evaluation
and review of the bids, there is a possibility that Mission, Orangewood, Grand Canal,
and Desert Garden Park could be included in the grant.
Bids received on Friday, May 11, 2012 are currently being reviewed and a Notice of
Intent to Award for this solicitation will be given to the most qualified and lowest
responsive and responsible bidder.
Council Sustainability Committee
May 15, 2012
Page 5
EECBG Summary
Approximately six weeks ago, the City met with the Department of Energy Project
Manager for an annual monitoring visit. This was a successful meeting as Glendale
met each goal associated with this grant. The Finance group who manages the
grant allocations was commended for their records keeping and other aspects of the
grant. The Department of Energy was very pleased with how the projects were
selected and how the work was completed. The three most important goals of the
grant, the creation of jobs, the reduction of greenhouse gases, and the reduction of
energy consumption were successfully met. According to the Department of Energy,
the projects created approximately 9.2 jobs for Glendale. It reduced greenhouse
gases by almost 700 metric tons of carbon dioxide equivalent, which equates to
taking 130 passenger vehicles off the road. The reduction in energy consumption
was the equivalent to 83 homes. The money saved over the life of the project and
reduced maintenance was projected at $99,000 annually in electricity costs.
Several discussions took place during and after the presentation, none of which
required any follow up or action on the part of staff. Vice-Mayor/ Chairperson Frate
and Councilmember Knaack thanked staff for the presentation. As this was an
informational item, no motion or vote was called for by the committee.
III. Staff Updates
Brad Tarrant, Energy Education Specialist reported that ASU's Sustainable Cities
Network (SCN) was recognized nationally by being awarded the President's Award
on April 18, 20112. In addition, Jo Miller who heads one of the SCN subcommittees
was recognized by ASU for her participation and leadership in the Network. The
Conservation and Sustainable Living program had two successful events recently.
The fifth Annual Glendale Green Festival on March 31, 2012, had approximately
1,200 residents and 45 vendors in attendance. Then on April 28, 2012, Glendale
celebrated the grand opening of the new Tree Trail at the Glendale Xeriscape
Garden with approximately 100 families in attendance.
ADJOURNMENT
The meeting was adjourned at approximately 11:10 a.m.
NEXT MEETING
The next meeting is scheduled for June 19, 2012, from 10:30 a.m. to 11:30 a.m. in
Conference Room B-2. The topic will be Water Services.
Respectfully Submitted,
Marilyn Clark ecording Secretary